Date |
Description |
8/11/2022 |
Tail kit for Sonex Model B has been ordered. |
10/20/2022 |
The Airframe kit has been ordered. This will be a Tri Gear kit with a Rotax Engine. |
11/11/2022 |
The tail kit arrives. Inventory completed. |
11/15/2022 |
Rudder is completed |
11/16/2022 |
Vertical Stabilizer forward spar is complete |
11/18/2022 |
Work on Vertical Stabilizer |
11/23/2022 |
Vertical Stabilizer completed |
11/25/2022 |
Work on Elevators |
11/27/2022 |
Horizonal Stabilizer work underway. |
12/5/2022 |
Horizonal stabilizer skinned. |
12/7/2022 |
Work benches updated with new tops. Tools cleaned and better organized. |
12/14/2022 |
Vertical stabilizer completed. tip installed. Will need to be cut for tail light. |
12/16/2022 |
Elevator completed. Horizonal stabilizer completed except for one wing tip. Need to order new parts. Cut too much fiberglass. |
1/13/2023 |
Horizonal Stabilizer Tips installed. Empennage is complete. |
3/30/2023 |
Airframe arrived! 6 boxes loaded into hanger. Starting Inventory |
|
|
|
|
|
|
|
|
|
|